Delivery Model · Concept to Qualified Production

How a GMP facility gets built.

A regulated plant is built once and audited for the rest of its life. Below is the sequence we work through with our clients: twenty stages from first requirements to a qualified, released facility, and the service line accountable at each one.

Stage 01 / 20 · Definition

User requirements & feasibility

Before geometry there is intent. We capture what the facility must make, at what scale, to which market's regulations, and test whether the business case survives contact with GMP reality. The URS written here is the document every later qualification protocol traces back to.

  • URS development
  • Capacity & batch modelling
  • Regulatory market scope
  • CapEx feasibility
Facility Engineering & Expansions

Stage 02 / 20 · Definition

Site selection & due diligence

A site is chosen on constraints, not on price alone. Utility headroom, effluent capacity, floor-to-underside height, floor loading, road access for module delivery, and room to expand later all get assessed before commitment. A cheap site that cannot take a 4 m ceiling void is not cheap.

  • Site & space evaluation
  • Utility headroom survey
  • Zoning & permitting review
  • Expansion allowance
Facility Engineering & Expansions

Stage 03 / 20 · Definition

Conceptual design & regulatory strategy

Room adjacencies fix personnel and material flow, and flow is what an inspector reads first. We set the classified envelope, the airlock positions, and the pressure cascade, then agree the regulatory strategy that the whole design will be defended against.

  • Process flow
  • Personnel / material segregation
  • Cascade strategy
  • Regulatory pathway
Facility Engineering & Expansions

Stage 04 / 20 · Design

Detailed design & design qualification

Concept becomes a buildable, defensible package: dimensioned layouts, HVAC zoning, utility schematics, and equipment schedules. Design qualification documents that the design meets the URS. Done properly here, it removes most of the findings that would otherwise surface during OQ.

  • Dimensioned GA drawings
  • HVAC zoning & load design
  • Utility schematics
  • DQ protocol
Commissioning, Qualification & Validation

Stage 05 / 20 · Design

Procurement & long-lead equipment

Cleanroom panels, AHUs, and filling equipment carry lead times measured in months, so procurement starts while design details are still closing. Vendor bids are evaluated technically rather than commercially, and footprints are reserved on the drawing before an order is placed.

  • URS-based bid evaluation
  • Vendor selection
  • Long-lead ordering
  • Footprint reservation
Equipment Engineering & Selection

Stage 06 / 20 · Construction

Civil works & building shell

Foundations, structural frame, roof, and envelope. The shell has to deliver the clear internal height the ceiling void needs and the floor loading the equipment demands. Both are effectively unfixable afterwards, which is why they are verified against the design before the frame closes.

  • Foundations & slab
  • Structural frame
  • Envelope & roof
  • Clear-height verification
Project Management

Stage 07 / 20 · Construction

Floor finishes

The slab is finished with seamless epoxy or welded vinyl, coved up the wall so there is no square internal corner anywhere a particle can sit. Falls to drain, load ratings, and equipment plinths are set now. Retrofitting them means breaking a qualified room open.

  • Seamless epoxy / vinyl
  • Coved skirting
  • Equipment plinths
  • Flatness survey
Project Management

Stage 08 / 20 · Construction

Walls

Modular GMP panel systems go up on the layout grid: flush-finished, non-shedding, with coved junctions at floor and ceiling. Panel joints are sealed and every service penetration is detailed before it is cut, because each one is a future leak on the room integrity test.

  • Modular GMP panels
  • Flush finish
  • Coved junctions
  • Sealed penetrations
Facility Engineering & Expansions

Stage 09 / 20 · Construction

Windows & doors

Double-glazed vision panels sit flush with the panel face on both sides, with no ledge, no reveal, and nothing to clean around. Sightlines let supervisors see a process without gowning into it, and door interlocks are wired so an airlock cannot be opened at both ends at once.

  • Flush double glazing
  • Supervision sightlines
  • Interlocked airlocks
  • Door hardware schedule
Facility Engineering & Expansions

Stage 10 / 20 · Construction

Cleanroom classification & airlocks

Each room is assigned its ISO 14644 class and its place in the pressure cascade, typically 10 to 15 Pa between adjacent grades, stepping down from the cleanest space outward. Gowning and material airlocks become the only routes across a classification boundary.

  • ISO 14644 classification
  • 10–15 Pa cascade
  • PAL / MAL airlocks
  • Gowning sequence
QMS & GMP Compliance

Stage 11 / 20 · Systems

HVAC ducting

Supply and return runs are routed above the corridor and branched to each room, sized for the air change rate that room's class demands. Ductwork is cleaned, capped, and pressure-tested to a declared leakage class before anything is closed in. That is the last moment at which a fault is cheap to find.

  • Supply / return routing
  • Volume control dampers
  • Leakage-class testing
  • Pre-install cleaning
Facility Engineering & Expansions

Stage 12 / 20 · Systems

AHU installation

The air handling unit is the room's lungs and its single largest running cost. Pre-filtration, cooling, reheat, and humidity control are staged in sequence, then tied to controls so temperature, humidity, and differential pressure are trended continuously rather than spot-checked.

  • Multi-stage filtration
  • Temperature & RH control
  • Fan & coil selection
  • ΔP trending
Automation & Digital Transformation

Stage 13 / 20 · Systems

Process utilities

Purified water, WFI, clean steam, compressed air, and process gases are distributed on sloped, drainable, dead-leg-free loops in sanitary stainless. Utility quality is a product quality attribute, so these systems carry their own qualification and ongoing monitoring programmes.

  • PW / WFI loops
  • Clean steam
  • Compressed air & gases
  • Dead-leg-free design
Facility Engineering & Expansions

Stage 14 / 20 · Systems

Electrical, BMS & EMS

Power distribution, emergency lighting, and containment are installed alongside the building management and environmental monitoring systems. The EMS is what proves the room stayed in a state of control between qualifications, so its sensor placement is a GMP decision, not an electrical one.

  • Power & containment
  • BMS integration
  • EMS sensor placement
  • Alarm & escalation logic
Automation & Digital Transformation

Stage 15 / 20 · Systems

Cleanroom ceiling & HEPA

A walkable ceiling closes the envelope and gives maintenance access from above, so filter changes never require entry into a classified room. Terminal HEPA housings are set on the grid, gel-sealed, then tested in place. The ceiling is where the room's cleanliness is finally made real.

  • Walkable ceiling grid
  • Terminal HEPA housings
  • Gel seal
  • In-situ filter integrity test
Facility Engineering & Expansions

Stage 16 / 20 · Equipment

Process equipment installation

Dispensing, granulation, compression, and coating equipment is set, levelled, connected to utilities, and run through site acceptance testing. Installation is documented to the standard IQ will demand, because re-creating that evidence later is far more expensive than capturing it now.

  • Setting & levelling
  • Utility connection
  • SAT execution
  • Installation records
Equipment Engineering & Selection

Stage 17 / 20 · Equipment

Packaging lines & serialization

Filling, capping, labeling, and case packing arrive as separate machines and have to leave as one line. We integrate vision inspection and serialization for track-and-trace, then tune changeover so the line speed on the quotation is the line speed on the floor.

  • Line integration
  • Serialization & aggregation
  • Vision inspection
  • Changeover optimization
Serialization

Stage 18 / 20 · Qualification

Commissioning

Systems are started, balanced, and proven to work before any qualification protocol is executed. Air balancing, cascade verification, control loop tuning, and punch-list closure happen here. Commissioning finds the engineering faults so that qualification can be about evidence rather than troubleshooting.

  • Air balancing
  • Cascade verification
  • Loop tuning
  • Punch-list closure
Commissioning, Qualification & Validation

Stage 19 / 20 · Qualification

Qualification & validation

Installation, operational, and performance qualification are executed against pre-approved protocols. Cleanroom classification is certified at rest and in operation, computer systems are validated for data integrity, and cleaning and process validation demonstrate the plant makes product reproducibly.

  • IQ / OQ / PQ
  • ISO 14644 certification
  • CSV & data integrity
  • Cleaning & process validation
Commissioning, Qualification & Validation

Stage 20 / 20 · Qualification

Handover & inspection readiness

Nothing is handed over until it is proven. The turnover package (drawings, protocols, deviations, SOPs, training records, maintenance schedules) is closed out and the quality system is live, so the facility can be inspected on day one rather than month six.

  • Turnover package
  • SOP & training
  • Preventive maintenance
  • Audit readiness
QMS & GMP Compliance
Ready when you are

Ready to scope your next project?

Tell us what you're building, expanding, or trying to get audit-ready. We'll respond with next steps, not a sales script.

Get in Touch